SBC Center Recent Construction Photos
Posted 6/25/02

Metal panel and cast stone installation continues on the west end of the building.


Steel at the Southwest Stair Tower is almost complete. Stairs and decking have begun on the Northeast and Southeast Stair Towers.


East entry bridge form work.


Terrazzo installation began at the East Entry. Microtopping and terrazzo installation will begin this week on the south side of the Main Concourse.


Ice piping installation is underway. The ice rink slab will pour the first week in July.


Seat installation began. Approximately 5,100 seats have been installed.