SBC Center Recent Construction Photos
Aug 27, 2002

The Ice Floor was poured on Saturday, July 27, beginning at 4:00 a.m.


The LED fascia panels encircling the bowl have been installed.


East Entry doors are being installed.


The final West Plaza Deck pour has occurred. The truck dock is now fully enclosed.


Landscaping and sidewalks are progressing at the East Entry. Paving will begin the middle of September.


East Entry Retaining wall rebar has been placed. Completion of retaining walls will be Wednesday of this week.


Landscape boulders have arrived on site for placement in landscape areas within the next few weeks.