Installation of electrical conduit in the beam cages on the Terrace Level in the Southeast Quadrant.


Tying reinforcing steel in a beam on the Terrace Level in the Southeast Quadrant.


Looking east from the Coliseum.


Installation of the ice rink piers.

To date: all 182 ice rink piers are complete.

1,117 of 1,188 (94%) complete. Now working on exterior piers around building.

6,437 cubic yards of concrete (715 trucks) for piers only.


Meanwhile, other sitework has resumed. Work on installation of Storm Drain Line "H" last week.

Runs from south side of Menger Creek to the south, parallel to Coliseum Road.

585 l.f. will be installed during Phase II sitework construction.